By the end of next year, a $5 million project to overhaul and rebuild much of LeClaire’s downtown district will be complete. At least that’s the plan and official schedule for a project centered around revamping about six blocks of North Cody Road between Ewing and Chestnut streets in LeClaire. The Cody Road Phase II […]
Already a subscriber? Log in
Want to Read More?
Get immediate, unlimited access to all subscriber content and much more.
Learn more in our subscriber FAQ.
- Unparalleled business coverage of the Iowa City / Cedar Rapids corridor.
- Immediate access to subscriber-only content on our website.
- 52 issues per year delivered digitally, in print or both.
- Support locally owned and operated journalism.
By the end of next year, a $5 million project to overhaul and rebuild much of LeClaire’s downtown district will be complete.
At least that’s the plan and official schedule for a project centered around revamping about six blocks of North Cody Road between Ewing and Chestnut streets in LeClaire.
The Cody Road Phase II Project will add sidewalks, crosswalks, a riverfront trail, storm sewer system improvements and much more aimed at spurring more development and bringing more businesses to the community.
In other words, “add to the charm” of downtown LeClaire in an effort to improve the community, said Jason Stangland, waterfront practice director with the Detroit-based Smith Group, the architectural, engineering and planning firm assist with the Cody Road project.
More than 50 people crowded into the LeClaire City Hall Council Chambers on Wednesday, March 8, for a public meeting to get more details on the project. Mr. Stangland and Leo Foley, city engineer for LeClaire and a project manager with the local engineering firm Veenstra & Kimm, provided many of those details.
Among the details discussed were:
- The Cody Street project is scheduled for completion by the end of next year.
- About 75% of the cost of the $5 million project will be paid for by a federal Surface Transportation Block Grant.
- Construction must start next year in order to receive that grant money.
Here is the proposed scheduled for the Cody Road project:
- Preliminary design to be done by April 14.
- Phase 2 plan public meeting by May 31.
- Preliminary plans to the Iowa Department of Transportation (IDOT) by Aug. 16.
- Check plans by Sept. 1.
- Final plans to IDOT by Oct. 19.
- Letting date by Jan. 19, 2024.
- Project construction to start March 1, 2024, and be complete by Dec. 30, 2024.